Boysun's work rhythms
The active phase of Boysun GPP construction is ongoing in the Surkhandarya region.
Specialists of Enter Engineering Group of Companies are fulfilling a wide range of work for implementation of the project "Engineering, procurement and construction of a gas processing plant, infrastructure facilities, gas gathering, treatment and transportation systems on a turnkey basis" under the production sharing agreement for "Uzbekiston mustakilligi” investment block.
The necessary logistics have been provided at the construction site of over the area of 70 hectares, construction of facilities and installation of equipment is underway, and the required materials are being delivered.
Construction and installation activities - concreting of foundations, erection of pipe racks and buildings, installation of process equipment, installation of steel structures, welding of underground pipelines - are dynamically underway at the gas processing plant. The sales gas pipeline, main source water conduit, access road with a bridge, fiber-optic communication lines (FOCL) are at the final stage of construction.
According to the plan, construction of storage facilities, preparation of site for 102 families residential town and a number of other facilities will be started in the near future.
Today, the project employs 929 people and uses 218 units of construction and road equipment.
Recall that the project provides for construction of a gas processing plant for annual production, processing and transportation of 5 billion m3. Production will be carried out using licensed technologies from Shell Global Solutions International B.V.