Work is in progress as scheduled
The active phase of construction of the Copper Concentration Plant (MOF-3) for AMMC, being implemented by Enter Engineering, continues.
To date, 60 K m3 of concrete has been poured and 11.7 K tons of reinforcement bar used.
2.7 K m3 has been excavated, and 1.5 M m3 has been drilled and blasted.
The Coarse Ore Stockpile (COS) area is being concreted and intermediate concrete slabs of 8 sections are being reinforced.
Structural work, installation of embedded parts and concreting are in progress at the Medium Ore Crushing Unit site. Installation of the Cone Crusher (КСД 3000) has begun.
Concrete for equipment foundation at Ore Preparation Unit and Fine Ore Crushing Unit is being poured.
In total 1989 workers and 654 units of heavy equipment: crawler dump trucks, cranes, bulldozers, excavators, concrete mixing trucks, etc. are currently involved in the project.
Following implementation of this major project, AMMC will be able to increase the volume of ore processing to 160 M tons per year, which will allow it increase the output of cathode copper to 400 K tons per year by 2028.